EARLIEST START TIME [2 records]

Record 1 2012-02-07

English

Subject field(s)
  • Organization Planning
DEF

In the critical path method, the earliest time that a schedule activity may be commenced.

CONT

Early dates are figured by a forward pass using a specific date and late dates are figured by using a backward starting from a completion date.

French

Domaine(s)
  • Planification d'organisation
DEF

Dans le contexte de la méthode du chemin critique, date la plus précoce à laquelle une activité de l'échéancier peut être commencée.

CONT

[...] Pour trouver [les relations entre les temps d'événement et d'activité,] il faut revenir au principe fondamental de calcul des dates au plus tôt des événements et des dates au plus tard des événements.

Spanish

Save record 1

Record 2 1975-03-11

English

Subject field(s)
  • Operations Research and Management
  • Organization Planning

French

Domaine(s)
  • Recherche et gestion opérationnelles
  • Planification d'organisation
DEF

c'est la date la plus proche à laquelle puisse commencer une activité, compte tenu des limitations s'imposant aux activités antérieures.

Spanish

Save record 2

Copyright notice for the TERMIUM Plus® data bank

© Public Services and Procurement Canada, 2026
TERMIUM Plus®, the Government of Canada's terminology and linguistic data bank
A product of the Translation Bureau

Features

GCtranslate (available on the Government of Canada network only)

Use this artificial intelligence prototype to translate Government of Canada content up to and including Protected B. Available to employees of selected departments and agencies only.

Writing tools

The Language Portal’s writing tools have a new look! Easy to consult, they give you access to a wealth of information that will help you write better in English and French.

Glossaries and vocabularies

Access Translation Bureau glossaries and vocabularies.

Date Modified: